Contract No:
HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing
Work (Stage 3) Environmental Permit no. EP-364/2009/D, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- april 2016 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
09 May 2016 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts
under the Project
Table 2.3 Contact Details of Key
Personnel
Table 3.1 Summary of the current status
on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.3 Summary of submission status
under FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.5 Summary of submission status
under FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary
of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/18
Table 5.2 Noise Monitoring
Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring
Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring Station
for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring Station
for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring Stations
for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal
for Contract no. HK/2009/01
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
¡P
Stage 3a
backfilling works
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Site
clearance works was on going at OHVD at Tunnel Portion 1.
¡P
Waterproofing
works and base slab construction were completed
¡P
Middle
wall and side wall construction
¡P
Diaphragm
wall panel construction
¡P
King post
work was completed
¡P
Instrumentation
work was on going
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Backfilling
works at TPCWAW
¡P
Dismantle
steel work at TPCWAW
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Remedial
works at Mined Tunnel
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no.
HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no.
HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at air quality
monitoring station CMA1b was rescheduled from 13 April 2016 to 14 April 2016
The 24hr TSP monitoring at air quality
monitoring station CMA3a was rescheduled from 01 April 2016 to 02 April 2016.
The 24hr TSP monitoring at air quality
monitoring station CMA5b was rescheduled from 13 April 2016 to 14 April 2016
Complaints, Notifications of Summons and Successful Prosecutions
ET confirmed with the Resident Site
Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and
blinding works for Manhole at Pier 34 were in progress on 22 March 2016.
The observed drain hole was identified
to be the outlet point of a manhole and a section of an abandoned U-channel
(extending from the concerned manhole to the Hong Kong Electric Substation in
length along the site boundary) was adjoining the concerned manhole and sandbag
was previously placed at the U-channel at the location near the inlet point to
the concerned manhole.
Based on the site records confirmed by
RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding
works for Manhole at Pier 34 were in progress on 22 March 2016. The observed
drain hole was identified to be the outlet point of a manhole and a section of
an abandoned U-channel (extending from the concerned manhole to the Hong Kong
Electric Substation in length along the site boundary) was adjoining the
concerned manhole and sandbag was previously placed at the U-channel at the
location near the inlet point to the concerned manhole. In addition, no site
discharge point was connected to the aforesaid U-channel and the concerned
manhole. In view of the environmental concern, the following remedial and
precautionary actions were taken by the Contractor of HY/2009/19 on 29 March
2016.
i)
Plugging
the inlet point of the concerned manhole (connecting to the abandoned
U-channel) with concrete;
ii)
Plugging
the outlet of the concerned manhole (connecting to the observed drain hole)
with concrete;
iii)
Filling
the concerned manhole with rubbles;
iv)
Shifting
the unused wastewater treatment plant around the concerned location to other
site location for use.
Follow-up inspection was conducted by
the Environmental Team on 06 April 2016. No further contaminated runoff
discharge was observed from the concerned drain hole and precautionary measures
including provision of concrete bunding was implemented along the site boundary
at the concerned location to avoid potential surface overflow. The pipe laying
works and the excavation works was found at distant location away from the
concerned drain hole with no surface drain connection and no particular
effluent was generated from the work. As such, no information indicate the
discharge was related to the above construction activities.
However, it was noted that another
section of surface drainage channel within the construction site (perpendicular
in direction to the initial identified abandoned U-channel) was also in
connection to concerned manhole and minor residue mud deposition was observed
within the surface drainage channel. Despite the above additional surface
drainage channel identified, the outlet point of concerned final manhole (in
connection with the observed drain hole) was observed plugged with concrete and
filled with rubbles as rectification measure to avoid any further contaminated
runoff discharge via the observed drain hole.
Nevertheless, the Contractor of
HY/2009/19 was reminded to conduct regular cleaning works for site surface
drainage channel to avoid accumulation of silt and soil and avoid potential
overflow by directing the surface runoff within the surface drainage channel to
proper collection point for necessary treatment prior to discharge. The
Contractor of HY/2009/19 was also reminded to check and review other surface
drainage channel within the construction site to avoid potential runoff related
impact via surface drainage channel to the nearby waters.
In addition, it was noticed that water
was discharged from a piping extending from City Garden and the discharged
water would result in seepage across the site hoarding into the abandoned
U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City
Garden Management Office for proper connection of the observed pipping with
discharge to prevent further seepage water into the construction site.
ET confirmed with the Resident Site
Staff that drilling holes for installation of starter bars was carried out
under Contract HY/2009/19 at the vertical cut face of the existing IEC road
slab on 05 April 2016
Based on the site records confirmed by
RSS, drilling holes for installation of starter bars was carried out under
Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on
05 April 2016 and according to the photo information provided by the EPD, no
dust suppression measures was implemented during the observed drilling works on
05 April 2016.
According to Air Pollution Control
Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water
or a dust suppression chemical shall be continuously sprayed on the surface
where any pneumatic or power-driven drilling, cutting, polishing or other
mechanical breaking operation that causes dust emission is carried out, unless
the process is accompanied by the operation of an effective dust extraction and
filtering device.
Follow-up inspection was conducted on 06
April 2016, rectification actions including the use of vacuum suction to
extract dust generated during the concerned drilling works was observed
implemented by the Contractor of HY/2009/19 for starter bars drilling works.
ET confirmed with the Resident Site
Staff that the concerned tree was identified as T710 and no construction
activity in the vicinity of tree T710 on 27 March 2016 and no construction
works are required in or near its vicinity.
Based on the site records confirmed by
RSS, the concerned tree was identified as the retained tree T710 maintained
under the Contract of HY/2010/08 and the concerned tree T710 was located
outside the assessment area in the relevant Project EIA Report. No construction
works are required in the vicinity of concerned tree T710 and no construction
activity was conducted in the vicinity of tree T710 on 27 March 2016.
Nevertheless, based on RSS information, recent tree monitoring report indicates
an existing cavity at trunk and the concerned tree T710 has been recommended to
be felled in the tree risk assessment Form 2.
With respect to the observed incident of
the toppling of the concerned tree T710, the Contractor of HY/2010/08 was
instructed by RSS to remove the broken trunk/ remains to avoid impact to the
surroundings. The concerned tree T710 shall be compensated by the Contractor of
HY/2010/08 in accordance with the Development Bureau Technical Circular (Works)
No. 7/2015 and the detail on compensation would be further agreed with Victoria
Park Management Office. Follow-up inspection was conducted on 13 April 2016,
and the remaining parts of the concerned tree T710 was observed felled to avoid
further impact to nearby public road.
ET confirmed with the Resident Site
Staff that no marine construction activities or land construction activities
under Contract HK/2009/02 at the concerned location on 12 April 2016.
Surface runoff control measures
including provision of concrete bund at the concerned location was implemented
by Contract HK/2009/02.
No soil & silt deposition along the
seawall at the concerned location on 12 April 2016.
No discharge point located in the
vicinity of the concerned location under Contract HK/2009/02.
Silt curtain with buoyancy floats acting
as anchor points was installed at Monitoring Station RW21-P789 for Water
intakes.
Based on the site records confirmed by
RSS, no marine construction activities or land construction activities was carried
out under Contract HK/2009/02 at the concerned location on 12 April 2016 and no
soil and silt deposition was found along the seawall at the concerned location
and precautionary measures for site runoff control including provision of
concrete bund along boundary of site area near the waterfront around the
concerned location was implemented by the Contractor HK/2009/02. In addition,
no discharge point under Contract HK/2009/02 was located in the vicinity of the
concerned location. Based on information confirmed by RSS, the buoyancy floats
deployed at the concerned location are acting as the anchor points for the silt
curtain deployed around the WQM Station RW21-P789 for the WSD and Cooling Water
Intakes group.
Follow-up inspection was conducted on 14
April 2016, no surface runoff from the construction site nor discharge of
contaminated effluent was observed around the concerned location and
precautionary measures including the provision of concrete bund at the
concerned location was observed maintained by the Contractor of HK/2009/02 and
the silt curtain deployed around the WQM station RW21-P789 was generally in
order.
In view of the public concern on the
water quality, the Contractor of HK/2009/02 was reminded to maintain effective
surface runoff protection and provide proper collection point of construction
effluent around the concerned location to avoid potential surface runoff
related impact.
ET confirmed with the Resident Site
Staff that internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos.
of dump trucks were deployed for the operation.
Protection measure including provision
of sandbag bunding along the side of the landing barge was implemented by the
Contractor of HK/2012/08.
According to the relevant site records
provided by RSS, internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3
nos. of dump trucks were deployed for the operation. Protection measure
including provision of sandbag bunding along the side of the landing barge was
implemented by the Contractor of HK/2012/08. In addition, amber rainstorm
warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and
during the above time period, muddy water was observed from the upstream of
culvert L outside the HK/2012/08 site.
Follow up inspection was conducted on 19
April 2016, protection measures including provision of sandbag bunding along
the side of the landing barge was implemented and no mud or soil deposition was
observed along the seawall and no discharge point was located within the
temporary water channel connecting the Culvert L outfall location to the
Victoria Harbour. In addition, piling works was observed at the north side of
Zone A1 on 19 April 2016 and construction effluent collection from piling work
via sedimentation tank to wastewater treatment facility was implemented and
steel barrier was installed around the piling works area to mitigate against
potential surface runoff related impact.
Nevertheless, in view of the public
concern, the Contractor was reminded to maintain adequate perimeter embankment
protection along the seawall boundary and maintain proper construction effluent
collection system to avoid potential runoff related impact to nearby waters.
Site Inspections and Audit
Future
Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at side wall slap application
¡P
Road side
barrier construction
¡P
Removal
of remaining temporary sheetpile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of ELS and backfilling works at TPCWAW
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
¡P
Saw
cutting of diaphragm wall at TPCWAW
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/D and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme
as stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/D, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B
during the period 27 March 2016 to 26 April 2016.
Section 1 Introduction ¡V details the scope
and structure of the report.
Section 2 Project
Background
¡V summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements
¡V summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results
¡V summarizes the monitoring results obtained in the reporting period.
Section 6 Compliance
Audit
¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site Audit ¡V summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any
relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V
summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Terry
Tsang |
6683 9394 |
|||
Environmental
Officer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant Environmental
Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214 7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214 7703 |
|||
Environmental Officer |
Mr. Chris Chan |
2823 1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Project
Manager |
Mr. Eddie
Chung |
9193 8871 |
|||
Site Agent |
Mr. Keith Tse |
9095 7922 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Y.L. Ho |
6050 4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung Kit
Cheung |
3557 6399 |
2566 8061 |
Project
Manager |
Chan Ying
Lun |
9812 0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467 4299 |
|||
Site Agent |
Dr. Dave Chan |
3467 4277 |
|||
Environmental
Officer |
Mr. C.M. Wong |
3557 6464 |
|||
Environmental
Supervisor |
Mr. Louis Lam
Tsz Kwan |
3557 6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul Evans |
2823 1111 |
21406799 |
Site Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 3a
backfilling works
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
¡P
Site
clearance works was on going at OHVD at Tunnel Portion 1.
¡P
Waterproofing
works and base slab construction were completed
¡P
Middle
wall and side wall construction
¡P
Diaphragm
wall panel construction
¡P
King post
work was completed
¡P
Instrumentation
work was on going
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Backfilling
works at TPCWAW
¡P
Dismantle
steel work at TPCWAW
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Remedial
works at Mined Tunnel
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at side wall slap application
¡P
Road side
barrier construction
¡P
Removal
of remaining temporary sheetpile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of ELS and backfilling works at TPCWAW
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
¡P
Saw
cutting of diaphragm wall at TPCWAW
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract
no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
20 Sep
2012 |
Superseded |
Environmental
Permit |
EP-364/2009/C |
11 Jul
2014 |
Superseded |
Environmental
Permit |
EP-364/2009/D |
24 Nov
2015 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26
July 2013 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Surrendered
|
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further
Environmental Permit |
24 Nov 2015 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Surrendered |
|
Further
Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS1134-15 |
23 Oct 2015 |
08 Nov 2015 to 07 May 2016 |
Valid |
GW-RS1135-15 |
23 Oct 2015 |
26 Nov 2015 to 25 May 2016 |
Valid |
|
GW-RS1228-15 |
13 Nov 2015 |
16 Nov 2015 to 13 May 2016 |
Valid |
|
GW-RS1309-15 |
27 Nov 2015 |
30 Nov 2015 to 26 May 2016 |
Valid |
|
GW-RS1338-15 |
11 Dec 2015 |
01 Jan 2016 to 30 June 2016 |
Valid |
|
GW-RS0041-16 |
22 Jan 2016 |
25 Jan 2016 to 23 Jul 2016 |
Valid |
|
GW-RS0089-16 |
05 Feb 2016 |
20 Feb 2016 to 19 July 2016 |
Valid |
|
GW-RS0093-16 |
05 Feb 2016 |
22 Feb 2016 to 21 July 2016 |
Valid |
|
GW-RS0152-16 |
18 Feb 2016 |
25 Feb 2016 to 24 Aug 2016 |
Valid |
|
GW-RS0243-16 |
11 Mar 2016 |
14 Mar 2016 to 13 Sep 2016 |
Valid |
|
GW-RS0384-16 |
19 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Valid |
|
Discharge License |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS1121-15 |
20 Oct 2015 |
22 Oct 2015 to 18 Apr 2016 |
Cancelled |
GW-RS1150-15 |
26 Oct 2015 |
28 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1187-15 |
28 Oct 2015 |
30 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1413-15 |
24 Dec 2015 |
02 Jan 2016 to 01 Jul 2016 |
Cancelled |
|
GW-RS1474-15 |
05 Jan 2016 |
08 Jan 2016 to 05 Apr 2016 |
Expired |
|
GW-RS0061-16 |
26 Jan 2016 |
29 Jan 2016 to 26 Apr 2016 |
Expired |
|
GW-RS0083-16 |
01 Feb 2016 |
3 Feb 2016 to 01 Aug 2016 |
Valid |
|
GW-RS0311-16 |
24 Mar 2016 |
25 Apr 2016 to 24 May 2016 |
Valid |
|
GW-RS0310-16 |
24 Mar 2016 |
27 Apr 2016 to 30 Apr 2016 |
Valid |
|
GW-RS0321-16 |
01 Apr 2016 |
5 Apr 2016 to 05 Jul 2016 |
Valid |
|
GW-RS0390-16 |
22 Apr 2016 |
27 Apr 2016 to 26 Oct 2016 |
Valid |
|
GW-RS0399-16 |
27 Apr 2016 |
27 Apr 2016 to 26 Oct 2016 |
Valid |
|
GW-RS0403-16 |
27 Apr 2016 |
30 Apr 2016 to 24 Sep 2016 |
Valid |
|
Water Discharge
License |
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
WT00009691-2011 |
01 Aug 2011 |
31 July 2016 |
Valid |
|
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
|
Billing Account
under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type
1 ¡V Open Sea Disposal) |
EP/MD/16-146 |
24 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP
Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
14 Jun
2011 |
Condition 1.12 |
Commencement Date of Works |
21 Jun
2011 |
Condition 2.11 |
Landscape Plan
(Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise
Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit /
Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit
issued |
Valid |
Notification
of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1206-15 |
06 Nov 2015 |
12 Nov 2015 to |
Expired |
GW-RS1383-15 |
14 Dec 2015 |
19 Dec 2015 to 27 Mar 2016 |
Cancelled |
|
GW-RS1415-15 |
24 Dec 2015 |
01 Jan 2016 to 30 Jun 2016 |
Valid |
|
GW-RS0057-16 |
26 Jan 2016 |
27 Jan 2016 to 31 Mar 2016 |
Expired |
|
GW-RS0335-16 |
7 Apr 2016 |
08 Apr 2016 to 30 Sep 2016 |
Valid |
|
Discharge
Licenses |
WT00013967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Cancelled |
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020725-2015 |
14 Jan 2015 |
30 Jul 2017 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract
no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1303-15 |
26 Nov 2015 |
26 Nov 2015 to 25 May 2016 |
Valid |
GW-RS1160-15 |
26 Oct 2015 |
28 Oct 2015 to 25 Apr 2016 |
Expired |
|
GW-RS0232-16 |
08 Mar 2016 |
9 Mar 2016 to 08 Sep 2016 |
Valid |
|
GW-RS0233-16 |
14 Mar 2016 |
14 Mar 2016 to 10 Sep 2016 |
Valid |
|
GW-RS0235-16 |
10 Mar 2016 |
12 Mar 2016 to 08 Sep 2016 |
Valid |
|
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jun 2016 |
Valid |
Billing Account under Waste Disposal
Ordinance (Disposal by Vessel) |
7011761 |
26 Jun 2015 |
17 Apr 2016 to 16 Jul 2016 |
Valid |
Water Discharge License (TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Expired |
Water Discharge License (Discharge at CHT area) |
WT00019250-2014 |
6 Jun 2014 |
06 Jun 2014 to 31 May 2016 |
Valid |
Water Discharge Licence (Discharge at TPCWAW) |
WT00020601-2014 |
18 Mar 2015 |
18 Mar 2015 to 31 Mar 2017 |
Valid |
Table 3.9 Summary of submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
11 Mar 2011 |
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar 2011 |
Condition 2.8 |
Location Plan |
15 Mar 2011 |
Condition 2.9 |
Noise Management Plan |
6 May 2011 |
Condition 2.10 |
Landscape Plan
(Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.10.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Superseded |
|
24 Nov 2015 |
N/A |
Valid |
||
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21 July
2011 |
N/A |
Valid |
Construction
Noise Permits (CNP) for non-piling equipment |
GW-RS1324-15 |
01 Dec 2015 |
08 Dec 2015 to 07 Jun 2016 |
Valid |
GW-RS1398-15 |
17 Jun 2015 |
18 Dec 2015 to 17 Jun 2016 |
Valid |
|
GW-RS0197-16 |
02 Mar 2016 |
02 Mar 2016 to 01 Sep 2016 |
Valid |
|
GW-RS0330-16 |
05 Apr 2016 |
05 Apr 2016 to 04 Oct
2016 |
Valid |
|
Water
Discharge License |
WT00010093-2011 |
17 Aug 2012 |
30 Sep 2016 |
Valid |
WT00010865-2011 |
03 Nov 2011 |
30 Nov 2016 |
Cancelled |
|
Dumping Permit (Approach
Ramp) (Type 1 ¡V Open Sea Disposal) |
EP/MD/16-092 |
20 Nov 2015 |
15 May 2016 |
Cancelled |
Table 3.11 Summary of submission status under FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition 2.13 |
Landscape Plan (Rev.4) |
22 March 2016 |
Condition 2.9 |
Noise Management Plan (Rev.4) |
15 February 2016 |
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West
3.1.11.
The
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-09/364/2009/B for contract no. HK/2012/08 showed in Table
3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
N/A |
Valid |
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0079-16 |
1 Feb 2016 |
3 Feb 2016 to 02 Aug 2016 |
Valid |
GW-RS0212-16 |
8 Mar 2016 |
10 Mar 2016 to 08 Sep 2016 |
Cancelled |
|
GW-RS0386-16 |
20 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Valid |
|
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table
3.13 Summary
of submission status under FEP-09/364/2009/B
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan (Rev.4) |
24 August 2015 |
Contract no.
HY/2010/08 ¡VCentral ¡V Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)
3.1.12.
The
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-10/364/2009/B for contract no. HK/2012/08 showed in Table
3.14 and Table 3.15.
Table
3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
|
Notification of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under Waste Disposal Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1061-15 |
30 Sep 2015 |
02 Oct 2015 to 31 Mar 2016 |
Cancelled |
GW-RS1063-15 |
30 Sep 2015 |
02 Oct 2015 to 31 Mar 2016 |
Cancelled |
|
GW-RS0001-16 |
06 Jan 2016 |
06 Jan 2016 to 05 Jun 2016 |
Valid |
|
GW-RW0061-16 |
02 Feb 2016 |
02 Feb 2016 to 31 Jul 2016 |
Valid |
|
GW-RS0264-16 |
18 Mar 2016 |
18 Mar 2016 to 17 Sep 2016 |
Valid |
|
GW-RS0357-16 |
22 Apr 2016 |
22 Apr 2016 to 21 Oct 2016 |
Valid |
|
GW-RS0362-16 |
22 Apr 2016 |
22 Apr 2016 to 21 Oct 2016 |
Valid |
|
GW-RS0407-16 |
20 Apr 2016 |
20 Apr 2016 to 19 Oct 2016 |
Valid |
|
GW-RS0434-16 |
05 May 2016 |
24 May 2016 to 23 Nov 2016 |
Valid |
|
GW-RS1137-15 |
22 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Expired |
|
GW-RS1141-15 |
20 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Expired |
|
GW-RS1145-15 |
20 Oct 2015 |
22 Oct 2015 to 21 Apr 2016 |
Expired |
|
GW-RS1262-15 |
17 Nov 2015 |
18 Nov 2015 to 16 May 2016 |
Valid |
|
GW-RS1282-15 |
25 Nov 2015 |
25 Nov 2015 to 24 May 2016 |
Valid |
Table
3.15 Summary
of submission status under FEP-10/364/2009/B
EP
Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan (Rev.3) |
03 January 2014 |
Condition
2.14 |
Landscape
Plan (Rev.2) |
19 May 2014 |
Condition
2.16 |
Additional
Mitigation Plan (Rev.2) |
18 February 2015 |
Contract no.
HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/B
3.1.13.
The
current status on licenses and/or permits on environmental protection pertinent
and submission under FEP-11/364/2009/B for contract no. HY/2011/08 showed in Table
3.16 and Table 3.17.
Table
3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
Notification of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Valid |
5213-151-L2837-02 |
09 Oct 2015 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
Billing Account under Waste Disposal Ordinance |
7019640 |
27 Mar 2014 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1235-15 |
12
Nov 2015 |
18
Nov 2015 to |
Valid |
GW-RS1369-15 |
14
Dec 2015 |
15
Dec 2015 to 31
May 2016 |
Valid |
|
GW-RS1423-15 |
24
Dec 2015 |
26
Dec 2015 to 31
May 2016 |
Valid |
|
GW-RS1426-15 |
29
Dec 2015 |
01
Jan 2016 to 30
Jun 2016 |
Valid |
|
GW-RS1433-15 |
29
Dec 2015 |
01
Jan 2016 to 30
Jun 2016 |
Valid |
|
GW-RS0147-16 |
17
Feb 2016 |
19
Feb 2016 to 31
Jul 2016 |
Valid |
|
GW-RS0159-16 |
17
Feb 2016 |
18
Feb 2016 to 31
Jul 2016 |
Valid |
|
GW-RS0222-16 |
8
Mar 2016 |
9
Mar 2016 to 31
Aug 2016 |
Valid |
|
GW-RS0284-16 |
23
Mar 2016 |
24
Mar 2016 to 31
Aug 2016 |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04 Nov
2014 |
30 Nov
2019 |
Valid |
WT00020246-2015 |
15 Jul
2015 |
31 Jul
2019 |
Valid |
Table 3.17 Summary
of submission status under FEP-11/364/2009/B
EP
Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan (Rev.2) |
27 Jan 2015 |
Condition
2.14 |
Landscape
Plan (Rev.2) |
18 Feb 2015 |
Condition
2.13 |
Operational
Air Quality Management Plan for West Ventilation Building (Rev.0) |
25 Nov 2014 |
Condition
2.13 |
Operational
Air Quality Management Plan for East Ventilation Building and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon-day Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
*M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
*M8 |
City
Hall |
* Remark 1: Location ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has become a reference station starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitfield Depot |
North Point |
RTN2a |
Hong Kong Electric Centre |
North
Point |
RTN3 |
Po Leung Kuk Yu Lee Mo Fan Memorial
School |
Tin
Hau |
RTN4 |
Causeway Bay Community Centre |
Noise Monitoring Parameters, Frequency
and Duration
4.1.3.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
One set
of measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 - hours basis when noise
generating activities are underway:
¡P
One set
of measurements between 0700 and 1900 hours on normal weekdays.
¡P
One set
of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
¡P
One set
of measurements between 2300 and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Site
Office** |
North
Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
CWB
PRE Site Office * |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan
Chai |
CMA5b |
Pedestrian
Plaza*** |
Wan
Chai |
MA1e |
International
Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International
Finance Centre (Western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as ¡§Oil Street Site Office¡¨
in April 2013.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air QUALITY Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring
Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
¡P
0.6 ¡V
1.7 m3 per minute adjustable flow range;
¡P
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
Capable
of providing a minimum exposed area of 406 cm2;
¡P
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
Equipped
with a shelter to protect the filter and sampler;
¡P
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
Equipped
with a flow recorder for continuous monitoring;
¡P
Provided
with a peaked roof inlet;
¡P
Incorporated
with a manometer;
¡P
Able to
hold and seal the filter paper to the sampler housing at horizontal position;
¡P
Easily
changeable filter; and
¡P
Capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24 hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of equipments
are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no. HK/2009/01
¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai West
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB)¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for
Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has
become a reference station starting from 7 Aug 2012
5.1.3
No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 ¡V Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
Two limit level exceedances were
recorded at M1a- Harbour Road Sports Centre on 29
March 2016 and 12 April 2016 in this reporting month.
5.1.7
Operation of multiple air compressor at Ex-
Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite
to the monitoring station) under non WDII-CWB Contractor was observed as the
major noise contribution during monitoring on 29 March 2016 while breaking works at Ex- Wan Chai
Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the
monitoring station) under non WDII-CWB Contractor as major noise contribution
during monitoring on 12 April 2016.
As such, the exceedances were considered as non-Project related.
5.1.8
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.9
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A
was on 13 July 2011. Noise monitoring was commenced on 13 July 2011.
The proposed divisions of noise monitoring stations are summarized in
Table 5.3 below.
Table 5.3
Noise Monitoring Stations
for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10
No action or limit level exceedance was
recorded in this reporting month.
5.1.11
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.1.12 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.13
Two limit level exceedances were recorded at
M6 ¡V HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016 in
the reporting month.
5.1.14
Traffic noise was observed during monitoring on
11 and 19 April 2016 and it was considered as the major noise contribution. As
such, the limit level exceedances were concluded as non-project related.
5.1.15
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 ¡V
Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.1.16
The commencement of construction works for
Contract no. HY/2010/08 under FEP-10/364/2009/B
was on 02 September 2013. Noise monitoring was commenced on 02 September 2013.
The proposed divisions of noise monitoring stations are summarized in
Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.17
No action or limit level exceedance was
recorded in this reporting month.
5.1.18
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.19 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6
Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station starting from 7 Aug 2012
5.1.20
No action or limit level exceedance was
recorded in this reporting month.
5.1.21
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real
time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13
Jan 2013. The baseline noise level of RTN4- Causeway Bay Community Centre has adopted
the results from the baseline noise monitoring report for EP/364/2009 in 22
April 2010 in which approved by EPD.
5.2.2.
Po Leung
Kuk Yu Lee Mo Fan Memorial School granted permission for set up on 4 Sep 2012
and real time noise monitoring station RTN3 set up was performed on 14 Sep
2012. Real time noise baseline capturing was conducted during time period
without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring
at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct
2012.
5.2.3.
Real-time
noise monitoring station RTN2 previously located at oil Street Community
Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct 2012, which
is a representative of the noise sensitive receiver City Garden. The baseline
noise level of RTN2a will adopt the results derived from the baseline noise
monitoring conducted at Hong Kong Electric Centre from 4 December 2009 to 17
December 2009.
5.2.4. Real-time noise monitoring station
RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD
Whitfield Depot on 24 June 2013 with respect to the commencement of advance
works for IEC parapet demolition.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.2.5.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 5.7 Real
Time Noise
Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North Point |
Hong Kong Electric Centre |
RTN3 |
North Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during restrict
hours and night time period are for information only and noise during CNP
period shall be controlled under NCO.
5.2.6.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.2.7.
Limit level exceedances were recorded at
RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during
daytime in the reporting month. On 02, 05 and 06 April 2016, only installation
of pre-cast parapet, pipe laying works and concreting of blinding layer for
pipe laying were undertaken by Contract HY/2009/19, no major noise concern of
the works was considered. On 08 April 2016, excavation and backfilling works
and erection of concrete surround were conducted and no major noise concern was
considered for the works. On 23 April 2016, backfilling works and concreting
for manhole cover were conducted and no major noise concern was considered for
the works. On 21, 25 and 26 April 2016, concreting and excavation for drain
pipe were conducted and no major noise concern was considered for the works. Nevertheless, roof top water proofing
works by non-CWB Contractor was undertaken immediately next to the noise
monitoring station across the monitoring period across April 2016 and was
considered as major noise contribution As such, the exceedances were considered
as non-Project related.
5.2.8.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School on 13, 18 and 25 April 2016 in the
reporting month. On 13, 18 and 25 April 2016 during the monitoring period, no
construction works was undertaken under Contract HY/2009/19. Nevertheless,
based on relevant data from Hong Kong observatory, adverse weather condition
with significant rainfall was recorded on 13, 18 and 25 April 2016 and
thunderstorm warning signal was hoisted on 13 and 25 April 2016 and considered
as the major noise contribution. As such, the exceedances were considered as
non-project related.
5.2.9.
Limit level exceedances were recorded at RTN4-Causeway
Bay Community Centre on 08 and 09 April 2016 in the reporting month. On 8 April
2016, minor vertical face drilling works was conducted and on 09 April 2016
crosshead concreting was conducted under HY/2009/19. In view of the same
construction sequence of vertical face drilling was extended to other time
period with no noise emanation recorded and drilling works immediately next to
the monitoring station by non-CWB Contractor for external panel installation at
Causeway Bay Community Centre was conducted on the monitoring date, the
exceedances were considered as non- Project related.
5.2.10.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 ¡V Central - Wan Chai
Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
5.2.11.
The proposed division of noise monitoring
stations are summarized in Table 5.8 below. Real time noise
monitoring for major construction works under contract no. HY/2011/08 was
commenced on 19 March 2015.
Table 5.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitfield Depot |
RTN2a1 |
North
Point |
Hong Kong Electric Centre |
* Real time noise monitoring results and graphical presentation during
restrict hours and night time period are for information only and noise during
CNP period shall be controlled under NCO.
Remarks 1: With respect to the possession of site area
Portion Xa and Portion Xb since 7 March 2016 as confirmed by CWB RSS, real time noise monitoring station RTN2a
was associated with Contract no. HY/2011/08 from 07 March 2016 onwards.
5.2.12.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.2.13.
Limit level exceedances were recorded at
RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during
daytime in the reporting month. No construction works was undertaken under
Contract HY/2011/08 on 02, 05, 06, 08, 21, 23 April 2016. On 25 April 2016,
site formation with one excavator in operation and on 26 April 2016, manual
rebar installation with coupler was conducted and no major noise concern was
considered for the above works Nevertheless, roof top water proofing works by
non-CWB Contractor was undertaken immediately next to the noise monitoring
station across the monitoring period across April 2016 and was considered as
major noise contribution As such, the exceedances were considered as
non-Project related.
Contract no. HY/2009/18 ¡V
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.1
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.9 below.
Table
5.9 Air Quality Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.2
No exceedance was recorded in the reporting
month.
5.3.3
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
One action level exceedance was recorded at
monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the
reporting month.
5.3.6
Only work activities within tunnel section
and no construction activities at ground was undertaken on the monitoring date
around Pedestrian Plaza under Contract HK/2009/01 and no particular observation
regarding air quality impact was observed during sampling. In view of the
above, the action level exceedance was considered to be non-project related and
contributed by local ambient condition.
5.3.7
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.8
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air quality monitoring stations are summarized in Table 5.11
below.
Table 5.11 Air Quality Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.9
No exceedance was recorded in the reporting
month.
5.3.10
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.11
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.12 below.
Table 5.12
Air
Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.12
No exceedance was recorded in the reporting
month.
5.3.13
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.3.14
The proposed division of air quality monitoring
stations are summarized in Table 5.13 below. Air quality monitoring
for the tunnel works under contract no. HY/2009/19 was commenced on 26 April
2011.
Table 5.13 Air Quality
Monitoring
Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.15
No exceedance was recorded in the reporting
month.
5.3.16
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II ¡V Central-Wan Chai Bypass at Wan Chai West
5.3.17
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.18
One action level exceedance was recorded at
monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the
reporting month.
5.3.19
After investigation, formwork erection and
internal transfer of excavated material were undertaken on the monitoring date
at around Pedestrian Plaza under Contractor of HK/2012/08, dust suppression
measure including haul road and excavated soil maintained in dampened condition
were implemented and no particular observation regarding air quality impact was
observed during sampling. In view of the above, the action level exceedance was
considered to be non-project related and contributed by local ambient
condition.
5.3.20
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 ¡V
Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.3.21
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15 below.
Table 5.15
Air
Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.22
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.23
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.16 below.
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.24
No exceedance was recorded in the reporting
month.
5.3.25
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
5.4.1.
Inert
C&D wastes and non-inert C&D wastes were disposed in this reporting
month. Details of the waste flow table are summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Waste Type |
|||
Inert
C&D materials disposed, m3 |
210.34 |
106340.92 |
TKO137, TM38 |
Inert
C&D materials recycled, m3 |
439.50 |
98492.03 |
N/A |
Non-inert
C&D materials disposed, m3 |
145.28 |
4527.34 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
8725.0 |
1143071 |
N/A |
Chemical
waste disposed, kg |
Nil |
10400 |
N/A |
Marine
Sediment (Type
1 ¡V Open Sea Disposal) , m3 |
Nil |
11527 |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
8669 |
480289.412 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
144 |
2577.317 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
17718 |
SENT Landfill |
Marine Sediment (Type 1 ¡V Open Sea Disposal) , m3 |
Nil |
27889 |
South Cheung Chau |
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
747.94 |
140052.86 |
||
Nil |
58787.05 |
||
26.53 |
4019.55 |
||
Nil |
878.37 |
||
Nil |
4440 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for
Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil Nil |
619726.37 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT |
Non-inert C&D materials disposed, m3 |
147.64 |
4248.84 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment (Type1-Open Sea Disposal
(Dedicate Sites) &Type 2 ¡V Confined Marine Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21 Details of
Waste Disposal for Contract no. HY/2009/19
Inert C&D
materials disposed, ton |
2090.61 |
649146.32 |
N/A |
Inert C&D
materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert C&D
materials disposed, ton |
221.68 |
4735.32 |
SENT Landfill |
Non-inert C&D
materials recycled, ton |
Nil |
548.4 |
N/A |
Chemical waste
disposed, kg |
Nil |
9.43 |
N/A |
Marine Sediment
(Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine Sediment
(Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 ¡V Confined
Marine Disposal), m3 |
Nil |
30751 |
East of Sha Chau |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table
5.22 Details of Waste Disposal for Contract
no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D
materials disposed, m3 |
12002 |
158673 |
TKO 137 |
Inert C&D
materials recycled, m3 |
10885 |
58954 |
N/A |
Non-inert C&D
materials disposed, m3 |
160 |
1470 |
SENT |
Non-inert C&D
materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste
disposed, kg |
Nil |
Nil |
N/A |
Marine sediment
(Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East of Sha Chau / South of The Brothers |
Contract no. HY/2010/08
Central ¡V Wan Chai Bypass (CWB) ¡V
Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
12262 52230.7 8254.2
6176.7 |
524876.3 173495.8 59944.5 10585.4 |
TM 38 WENT SENT TKO area 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
146.6 |
1818.46 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
979 |
N/A |
Table 5.23 Details of Waste Disposal for
Contract no. HY/2010/08
Contract no. HY/2011/08
Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table
5.24 Details of Waste Disposal for
Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil |
367.68 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
40.9 |
691.58 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.1.1. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II
¡V Central ¡V Wan Chai Bypass at Hong Kong Convention Exhibition Centre ¡V Tunnel
Works under FEP-02/364/2009
6.1.2. Two limit level
exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016
and 12 April 2016 in this reporting month.
6.1.3. Operation of
multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road
Sports Centre directly opposite to the monitoring station) under non WDII-CWB
Contractor was observed as the major noise contribution during monitoring on 29
March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to
Habour Road Sports Centre directly opposite to the monitoring station) under
non WDII-CWB Contractor as major noise contribution during monitoring on 12
April 2016. As such, the exceedances
were considered as non-Project related.
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4. Two limit level
exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016
and 12 April 2016 in this reporting month.
6.1.5. Operation of
multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road
Sports Centre directly opposite to the monitoring station) under non WDII-CWB
Contractor was observed as the major noise contribution during monitoring on 29
March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to
Habour Road Sports Centre directly opposite to the monitoring station) under
non WDII-CWB Contractor as major noise contribution during monitoring on 12
April 2016. As such, the
exceedances were considered as non-Project related.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.6. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.7. Two limit level
exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School
on 11 and 19 April 2016 in the reporting month.
6.1.8. Traffic noise
was observed during monitoring on 11 and 19 April 2016 and it was considered as
the major noise contribution. As such, the limit level exceedances were
concluded as non-project related.
Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Raod 8
Section) under FEP-10/364/2009/B
6.1.9. No exceedance
was recorded in the reporting month.
Contract no. HY/2011/08 Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.10. No exceedance
was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.11. No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
6.1.12. Limit level exceedances
were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26
April 2016 during daytime in the reporting month. On 02, 05 and 06 April 2016,
only installation of pre-cast parapet, pipe laying works and concreting of
blinding layer for pipe laying were undertaken by Contract HY/2009/19, no major
noise concern of the works was considered. On 08 April 2016, excavation and
backfilling works and erection of concrete surround was conducted and no major
noise concern was considered for the works. On 23 April 2016, backfilling works
and concreting for manhole cover were conducted and no major noise concern was
considered for the works. On 21, 25 and 26 April 2016, concreting and
excavation for drain pipe was conducted and no major noise concern was
considered for the works.
Nevertheless, roof top water proofing works by non-CWB Contractor was
undertaken immediately next to the noise monitoring station across the
monitoring period across April 2016 and was considered as major noise
contribution As such, the exceedances were considered as non-Project related.
6.1.13. Limit level
exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 13, 18 and
25 April 2016 in the reporting month. On 13, 18 and 25 April 2016 during the
monitoring period, no construction works was undertaken under Contract
HY/2009/19. Nevertheless, based on relevant data from Hong Kong observatory,
adverse weather condition with significant rainfall was recorded on 13, 18 and
25 April 2016 and thunderstorm warning signal was hoisted on 13 and 25 April
2016 and considered as the major noise contribution. As such, the exceedances
were considered as non-project related.
6.1.14. Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre on 08 and 09
April 2016 in the reporting month. On 8 April 2016, minor vertical face
drilling works was conducted and on 09 April 2016 crosshead concreting was
conducted under HY/2009/19. In view of the same construction sequence of
vertical face drilling was extended to other time period with no noise
emanation recorded and drilling works immediately next to the monitoring station
by non-CWB Contractor for external panel installation at Causeway Bay Community
Centre was conducted on the monitoring date, the exceedances were considered as
non- Project related.
Contract no. HY/2011/08
Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.15. No limit level exceedance was recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot in the reporting month.
6.1.16. Limit level exceedances were recorded at
RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during
daytime in the reporting month. No construction works was undertaken under
Contract HY/2011/08 on 02, 05, 06, 08, 21, 23 April 2016. On 25 April 2016,
site formation with one excavator in operation and on 26 April 2016, manual
rebar installation with coupler was conducted and no major noise concern was
considered for the above works. Nevertheless, roof top water proofing works by
non-CWB Contractor was undertaken immediately next to the noise monitoring
station across the monitoring period across April 2016 and was considered as
major noise contribution As such, the exceedances were considered as
non-Project related.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
6.2.2.
One action level exceedance was recorded at
monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the
reporting month.
6.2.3.
Only work activities within tunnel section
and no construction activities at ground was undertaken on the monitoring date
around Pedestrian Plaza under Contract HK/2009/01 and no particular observation
regarding air quality impact was observed during sampling. In view of the
above, the action level exceedance was considered to be non-project related and
contributed by local ambient condition.
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) FEP-06/364/2009/A
6.2.5.
No exceedance was recorded in the reporting
month.
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.6.
No exceedance was recorded in the reporting
month.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
6.2.7.
One action level exceedance was recorded at
monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the
reporting month.
6.2.8.
After investigation, formwork erection and
internal transfer of excavated material were undertaken on the monitoring date
at around Pedestrian Plaza under Contractor of HK/2012/08, dust suppression
measure including haul road and excavated soil maintained in dampened condition
were implemented and no particular observation regarding air quality impact was
observed during sampling. In view of the above, the action level exceedance was
considered to be non-project related and contributed by local ambient
condition.
Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Raod 8
Section) under FEP-10/364/2009/B
6.2.9.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08
Central ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.2.10.
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits and monitoring in the reporting period. The observations and
recommendations made in each individual site audit session were presented in
Section 8.
6.3.2.
With respect to the complaint case referred
by EPD received by ET on 05 April 2016 (Case Ref.:H08/RS/00007662-16). The
complainant reported that construction dust emission arising from drilling
activity from the construction site of Central ¡V Wan Chai Bypass ¡V Tunnel
(North Point Section) and Island Eastern Corridor Link (Contract No.
HY/2009/19).
6.3.3.
Based on the site records confirmed by RSS,
drilling holes for installation of starter bars was carried out under Contract
HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April
2016 and according to the photo information provided by the EPD, no dust
suppression measures was implemented during the observed drilling works on 05
April 2016. According to Air
Pollution Control Ordinance, for pneumatic or power-driven drilling, cutting
and polishing, water or a dust suppression chemical shall be continuously
sprayed on the surface where any pneumatic or power-driven drilling, cutting,
polishing or other mechanical breaking operation that causes dust emission is
carried out, unless the process is accompanied by the operation of an effective
dust extraction and filtering device.
6.3.4.
Based on
the information advised by the CWB RSS on 05 May 2016, a case of construction
noise permit contravention under Contract HY/2009/19 was identified by the EPD
on 24 April 2016.
6.4.1
With respect to the identified case on
drilling works without dust suppression measures, follow-up inspection was
conducted on 06 April 2016, rectification actions including the use of vacuum
suction to extract dust generated during the concerned drilling works was
observed implemented by the Contractor of HY/2009/19 for starter bars drilling
works.
6.4.2
A Record of Inspection regarding the drilling
works conducted on 05 April 2016 was subsequently issued by the EPD to the
Contractor of HY/2009/19 on 21 April 2016.
6.4.3
With respect to the identified case on
contravention on construction noise permit (Contract HY/2009/19), the
construction noise permit no. GW-RS197-16 was cancelled by the Authority on 27
April 2016.Further information to be submitted by the Contractor of HY/2009/19
and CWB RSS team was requested by the Environmental Team for follow up.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/C, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area
include structural works for tunnel construction, road works and drainage works,
removal of bulkhead wall and landscape establishment works were performed in April
2016 reporting month. As no project related exceedance were
recorded during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4. According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were
tunnel works, D-wall construction at Wan Chai East and culvert construction,
piling and ELS works at Wan Chai West. The major construction
activities under Central-Wan Chai Bypass and Island Eastern Corridor Link
Projects were bridge construction and road works at Central Interchange, backfilling
works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park,
ELS works and tunnel works at TS3; bridge construction, piling and tunnel works
at North Point area in the reporting month. In addition, other non-Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects was observed undertaken at Wan Chai North area.
7.0.5.
No significant air quality impact from
construction activities was anticipated in the reporting month. Besides, no project
related exceedance was recorded during the air quality and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08.
No non-conformance was identified during the site audits. The Contractors rectified major observations and recommendations made
during the audit sessions. No non-conformance was identified during the site
inspections.
8.0.2.
Site inspections for Contract no. HY/2009/15
were carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160405_1 |
5 Apr 2016 |
Tarpaulin
shall be provide between barge and seawall to avoid drop off during material
transportation process (EX-PCWA
North) |
Tarpaulin
sheet was provided to material transportation process |
Completion
as observed on 12 April 2016 |
160412_1 |
12 Apr
2016 |
Dust
suppression measures shall be provided to breaking works. (EX-PCWA
Site Entrance) |
No further
breaking works was observed |
Completion
as observed on 19 April 2016 |
160412_2 |
12 Apr
2016 |
The soil
material left on the top of the seawall
block shall be cleared to avoid runoff impact. (Ex-PCWA) |
Soil left
on the top of seawall block was cleared |
Completion
as observed on 26 April 2016 |
8.0.3.
Site inspections for Contract no. HY/2009/18
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160407_1 |
7 Apr 2016 |
Waste water generated from works
process shall not directly wash into drainage system .For works could
generate waste water, protection shall be treated properly before discharge (P1 Road) |
No further
waste water generation activities was observed |
Completion
as observed on 14 April 2016 |
160421_1 |
21 Apr
2016 |
Remove the
electric distribution box away from retained tress onsite and provide
protection for exposed roots |
Remove the
electric distribution box away from retained tress onsite and protection was
provided to retained tree with exposed roots |
Completion
as observed on 25 April 2016 |
160421_2 |
21 Apr
2016 |
Provide
dust suppression e.g. dampening of surface during polishing works to avoid
dust emission. |
No further
polishing works was observed |
Completion
as observed on 25 April 2016 |
160425_1 |
25 Apr
2016 |
Watering
and covering shall be provided to stockpile and material process |
Covering
was provided to stockpile stored on-site |
Completion
as observed on 5 May 2016 |
8.0.4.
Site inspections for Contract no. HY/2009/19
were carried out during this reporting period. No observation was found in the
reporting month.
8.0.5.
Site inspections for Contract no. HK/2009/01
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.4.
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/01
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160421_01 |
21 Apr
2016 |
Wheel
washing and vehicle control at Gate 1 shall be improved to a controlled
manner to avoid muddy trail on public road. |
Vehicle
control was implemented properly and no muddy trail was observed on the
public road. |
Completion
as observed on 27 April 2016 |
8.0.6.
Site inspections for Contract no. HK/2009/02
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.5.
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160428_01 |
28 Apr
2016 |
Drip trays
shall be provided for all oil containers at Portion 3&4 |
Drip tray
were provided for oil containers at Portion 3&4 |
Completion
as observed on 5 May 2016 |
160428_02 |
28 Apr
2016 |
Leaked oil
from plant shall be properly collected as soon as possible at Portion 5. |
Leaked oil
was cleaned at Portion 5. |
Completion
as observed on 5 May 2016 |
8.0.7.
Site inspection for Contract no. HK/2012/08
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.6.
Table 8.6 Summary of Environmental Inspections for
Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160329_01 |
29 Mar
2016 |
Oil
container shall be properly placed to prevent it from falling down at Zone A2
(2) |
Oil
container was removed at Zone A2 (2). |
Completion
as observed on 5 April 2016 |
160412_01 |
12 Apr
2016 |
Drip tray
shall be provided for oil container at Zone D |
Oil
container was removed at Zone D. |
Completion
as observed on 19 April 2016 |
8.0.8.
Site inspections for Contract no. HY/2010/08
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.7
Table 8.7 Summary of Environmental Inspections for
Contract no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion
date |
160330_1 |
30 Mar 2016 |
The temporary reclamation removal works shall be conducted
according to the agreed method statement (removal of excavated material down
to -4.5mpD prior to seawall block removal)and the deployment of impermeable
barrier shall follow the method statement arrangement(TS3) |
Impermeable barrier was provided to works area around excavated
area |
Completion as observed on 8 April 2016 |
160330_2 |
30 Mar 2016 |
The silt curtain shall be fully deployed to seabed(TS3) |
The silt curtain was fully deployed to seabed |
Completion as observed on 8 April 2016 |
160408_1 |
8 Apr 2016 |
Covering the stockpile stored on-site to avoid potential dust
emission(Victoria Park) |
Stockpile stored on-site was covered by impervious sheeting |
Completion as observed on 13 April 2016 |
160408_2 |
8 Apr 2016 |
Clear the floating oil and scum around the intake location within
the site area and check the integrity of the site screen installed (TS3) |
Floating refuses and scum were cleared |
Completion as observed on 13 April 2016 |
160408_3 |
8 Apr 2016 |
The silt curtain maintained around the derrick barge shall be
maintained free of gap(TS3) |
The gaps between silt curtain has been tighten |
Completion as observed on 13 April 2016 |
160413_1 |
13 Apr 2016 |
Tarpaulin covering shall be provided for stockpile stored on site
to avoid dust and runoff impact (Victoria Park) |
Stockpile stored on-site was covered by impervious sheeting |
Completion as observed on 20 April 2016 |
160413_2 |
13 Apr 2016 |
Clear the oil within the silt screen system and leaked oil on
land as chemical waste (TS3) |
Oil within the silt screen and leaked oil on land was cleared |
Completion as observed on 20 April 2016 |
160413_3 |
13 Apr 2016 |
Rectify the damaged boundary embankment protection to prevent
contaminated surface overflow (TS3) |
The damaged section of embankment was repaired |
Completion as observed on 20 April 2016 |
160413_4 |
13 Apr 2016 |
Impermeable barrier shall be deployed according to the method
statement to enclose the work area carrying out excavation from -4.35mpD to
-7mpD and ensure no gap between the silt curtain deployed and all silt
curtain and silt screen shall be fully deployed to seabed level (TS3)\ |
Impermeable barrier was provided to the concerned works area and
silt curtain was tighten and deploy to the seabed |
Completion as observed on 20 April 2016 |
160413_5 |
13 Apr 2016 |
Review the adequacy of treatment capacity of the water treatment
plant and suitable measure shall be provided to avoid potential water quality
impact (TS3) |
Water treatment plant was operated with adequate capacity and
silt curtain was deploy around the discharge point |
Completion as observed on 20 April 2016 |
160420_1 |
20 Apr 2016 |
Muddy seepage at the impermeable barrier was observed. The
impermeable barrier deploy shall be tightened and to avoid gap at the end and
silt curtain shall be provided during seawall removal (TS3) |
Impermeable barrier was tighten and no further muddy seepage was
observed |
Completion as observed on 27 April 2016 |
160420_2 |
20 Apr 2016 |
Boundary bunding protection shall be provided along the entire
section of the northern side of seawall and clear the mud deposit along the
seawall to avoid runoff impact(TS3 North) |
Boundary bunding was provided along the northern side of seawall |
Completion as observed on 27 April 2016 |
8.0.9.
Site inspections for Contract no. HY/2011/08
were carried out during this reporting period. No observation was found in the
reporting month.
9.0.1.
Five
environmental complaints were received in the reporting month.
9.0.2.
First
public complaint regarding direct discharge of muddy effluent referred by EPD
was received by ET on 31 March 2016 (Case Ref.: H08/RS/00006732-16). The
complainant reported that muddy water was observed discharged from the
construction site of Central ¡V Wan Chai Bypass ¡V Tunnel (North Point Section)
and Island Eastern Corridor Link (Contract No. HY/2009/19) into Victoria Habour
via a drain hole.
ET confirmed with the Resident Site
Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and
blinding works for Manhole at Pier 34 were in progress on 22 March 2016.
The observed drain hole was identified
to be the outlet point of a manhole and a section of an abandoned U-channel
(extending from the concerned manhole to the Hong Kong Electric Substation in
length along the site boundary) was adjoining the concerned manhole and sandbag
was previously placed at the U-channel at the location near the inlet point to
the concerned manhole.
Based on the site records confirmed by
RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding
works for Manhole at Pier 34 were in progress on 22 March 2016. The observed
drain hole was identified to be the outlet point of a manhole and a section of
an abandoned U-channel (extending from the concerned manhole to the Hong Kong
Electric Substation in length along the site boundary) was adjoining the
concerned manhole and sandbag was previously placed at the U-channel at the
location near the inlet point to the concerned manhole. In addition, no site
discharge point was connected to the aforesaid U-channel and the concerned
manhole. In view of the environmental concern, the following remedial and
precautionary actions were taken by the Contractor of HY/2009/19 on 29 March
2016.
i) Plugging
the inlet point of the concerned manhole (connecting to the abandoned
U-channel) with concrete;
ii) Plugging
the outlet of the concerned manhole (connecting to the observed drain hole)
with concrete;
iii) Filling
the concerned manhole with rubbles;
iv) Shifting
the unused wastewater treatment plant around the concerned location to other
site location for use.
Follow-up inspection was conducted by
the Environmental Team on 06 April 2016. No further contaminated runoff
discharge was observed from the concerned drain hole and precautionary measures
including provision of concrete bunding was implemented along the site boundary
at the concerned location to avoid potential surface overflow. The pipe laying
works and the excavation works was found at distant location away from the
concerned drain hole with no surface drain connection and no particular
effluent was generated from the work. As such, no information indicate the
discharge was related to the above construction activities.
However, it was noted that another
section of surface drainage channel within the construction site (perpendicular
in direction to the initial identified abandoned U-channel) was also in
connection to concerned manhole and minor residue mud deposition was observed
within the surface drainage channel. Despite the above additional surface
drainage channel identified, the outlet point of concerned final manhole (in
connection with the observed drain hole) was observed plugged with concrete and
filled with rubbles as rectification measure to avoid any further contaminated
runoff discharge via the observed drain hole.
Nevertheless, the Contractor of
HY/2009/19 was reminded to conduct regular cleaning works for site surface
drainage channel to avoid accumulation of silt and soil and avoid potential
overflow by directing the surface runoff within the surface drainage channel to
proper collection point for necessary treatment prior to discharge. The
Contractor of HY/2009/19 was also reminded to check and review other surface
drainage channel within the construction site to avoid potential runoff related
impact via surface drainage channel to the nearby waters.
In addition, it was noticed that water
was discharged from a piping extending from City Garden and the discharged
water would result in seepage across the site hoarding into the abandoned
U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City
Garden Management Office for proper connection of the observed pipping with
discharge to prevent further seepage water into the construction site.
9.0.3.
Second
public complaint regarding construction dust emission was referred by EPD was
received by ET on 05 April 2016 (Case Ref.: H08/RS/00007662-16). The
complainant reported that construction dust emission arising from drilling
activity from the construction site of Central ¡V Wan Chai Bypass ¡V Tunnel
(North Point Section) and Island Eastern Corridor Link (Contract No.
HY/2009/19).
ET confirmed with the Resident Site
Staff that drilling holes for installation of starter bars was carried out
under Contract HY/2009/19 at the vertical cut face of the existing IEC road
slab on 05 April 2016.
Based on the site records confirmed by
RSS, drilling holes for installation of starter bars was carried out under
Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on
05 April 2016 and according to the photo information provided by the EPD, no
dust suppression measures was implemented during the observed drilling works on
05 April 2016.
According to Air Pollution Control
Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water
or a dust suppression chemical shall be continuously sprayed on the surface
where any pneumatic or power-driven drilling, cutting, polishing or other
mechanical breaking operation that causes dust emission is carried out, unless
the process is accompanied by the operation of an effective dust extraction and
filtering device.
Follow-up inspection was conducted on 06
April 2016, rectification actions including the use of vacuum suction to
extract dust generated during the concerned drilling works was observed
implemented by the Contractor of HY/2009/19 for starter bars drilling works.
9.0.4.
Third
public complaint regarding landscape aspect was referred by RSS was received by
ET on 11 April 2016 (Case Ref.:2-2036525055). The complainant reported that a
tree (6 meters in height and 1.5 meters in diameter) was found toppled at 111
Victoria Park Road, near Lamp post 38632 and blocking the Pedestrian pathway on
27 March 2016.
ET confirmed with the Resident Site
Staff that the concerned tree was identified as T710 and no construction activity
in the vicinity of tree T710 on 27 March 2016 and no construction works are
required in or near its vicinity.
Based on the site records confirmed by
RSS, the concerned tree was identified as the retained tree T710 maintained
under the Contract of HY/2010/08 and the concerned tree T710 was located
outside the assessment area in the relevant Project EIA Report. No construction
works are required in the vicinity of concerned tree T710 and no construction
activity was conducted in the vicinity of tree T710 on 27 March 2016.
Nevertheless, based on RSS information, recent tree monitoring report indicates
an existing cavity at trunk and the concerned tree T710 has been recommended to
be felled in the tree risk assessment Form 2.
With respect to the observed incident of
the toppling of the concerned tree T710, the Contractor of HY/2010/08 was
instructed by RSS to remove the broken trunk/ remains to avoid impact to the
surroundings. The concerned tree T710 shall be compensated by the Contractor of
HY/2010/08 in accordance with the Development Bureau Technical Circular (Works)
No. 7/2015 and the detail on compensation would be further agreed with Victoria
Park Management Office. Follow-up inspection was conducted on 13 April 2016,
and the remaining parts of the concerned tree T710 was observed felled to avoid
further impact to nearby public road.
9.0.5.
Forth
public complaint regarding muddy dispersion referred by RSS was received by ET
on 13 April 2016. The complainant reported that muddy water was observed to
disperse from Contract HK/2009/02 site area to Victoria Harbour occasionally as
there was no silt curtain installed under the buoyancy floats. The location
concerned was the East of Star Ferry Piers (Contract No. HK/2009/02).
ET confirmed with the Resident Site
Staff that no marine construction activities or land construction activities
under Contract HK/2009/02 at the concerned location on 12 April 2016.
Surface runoff control measures
including provision of concrete bund at the concerned location was implemented
by Contract HK/2009/02.
No soil & silt deposition along the
seawall at the concerned location on 12 April 2016.
No discharge point located in the
vicinity of the concerned location under Contract HK/2009/02.
Silt curtain with buoyancy floats acting
as anchor points was installed at Monitoring Station RW21-P789 for Water
intakes.
Based on the site records confirmed by
RSS, no marine construction activities or land construction activities was
carried out under Contract HK/2009/02 at the concerned location on 12 April
2016 and no soil and silt deposition was found along the seawall at the
concerned location and precautionary measures for site runoff control including
provision of concrete bund along boundary of site area near the waterfront
around the concerned location was implemented by the Contractor HK/2009/02. In
addition, no discharge point under Contract HK/2009/02 was located in the
vicinity of the concerned location. Based on information confirmed by RSS, the
buoyancy floats deployed at the concerned location are acting as the anchor
points for the silt curtain deployed around the WQM Station RW21-P789 for the
WSD and Cooling Water Intakes group.
Follow-up inspection was conducted on 14
April 2016, no surface runoff from the construction site nor discharge of
contaminated effluent was observed around the concerned location and
precautionary measures including the provision of concrete bund at the
concerned location was observed maintained by the Contractor of HK/2009/02 and
the silt curtain deployed around the WQM station RW21-P789 was generally in
order.
In view of the public concern on the
water quality, the Contractor of HK/2009/02 was reminded to maintain effective
surface runoff protection and provide proper collection point of construction
effluent around the concerned location to avoid potential surface runoff
related impact.
9.0.6.
Fifth
public complaint regarding muddy water discharge referred by EPD was received
by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The
complainant reported that muddy water was discharged from the construction work
of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing
Arts on 13 April 2016 morning.
ET confirmed with the Resident Site
Staff that internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3
nos. of dump trucks were deployed for the operation.
Protection measure including provision
of sandbag bunding along the side of the landing barge was implemented by the
Contractor of HK/2012/08.
According to the relevant site records
provided by RSS, internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3
nos. of dump trucks were deployed for the operation. Protection measure
including provision of sandbag bunding along the side of the landing barge was
implemented by the Contractor of HK/2012/08. In addition, amber rainstorm
warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and
during the above time period, muddy water was observed from the upstream of
culvert L outside the HK/2012/08 site.
Follow up inspection was conducted on 19
April 2016, protection measures including provision of sandbag bunding along
the side of the landing barge was implemented and no mud or soil deposition was
observed along the seawall and no discharge point was located within the
temporary water channel connecting the Culvert L outfall location to the
Victoria Harbour. In addition, piling works was observed at the north side of
Zone A1 on 19 April 2016 and construction effluent collection from piling work
via sedimentation tank to wastewater treatment facility was implemented and
steel barrier was installed around the piling works area to mitigate against
potential surface runoff related impact.
Nevertheless, in view of the public
concern, the Contractor was reminded to maintain adequate perimeter embankment
protection along the seawall boundary and maintain proper construction effluent
collection system to avoid potential runoff related impact to nearby waters.
9.0.7.
The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1
9.0.8. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
April 2016 |
5 |
September 2010 ¡V March 2016 |
59 |
Total |
64 |
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in
Coming Reporting Month
Contract
No. |
Key Construction
Works |
Recommended
Mitigation Measures |
HY/2009/15 |
¡P
Remedial
works at Mined Tunnel ¡P
Remaining
works inside tunnel at TS4 and TPCWAE ¡P
Removal
of ELS and backfilling works at TPCWAW ¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE ¡P
Saw
cutting of diaphragm wall at TPCWAW |
¡P
Dust
control during dust generating activities and covering for stockpile stored
on site. ¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the nearby water. ¡P
Maintain
regular cleaning of floating refuses within construction area. |
HY/2009/18 |
¡P
Drainage
works ¡P
Road
works ¡P
Landscaping
works ¡P
Modification
and Construction of Sign Gantries / Traffic Signs ¡P
Maintenance
works |
¡P
Dust
control during dust generating activities ¡P
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. |
HY/2009/19 |
¡P
Pier
construction for IEC ¡P
Construction
of EVB ¡P
Column
modification at F1 to F8 ¡P
Watson
Road laying of new water pipe ¡P
Oil
Street drainage works ¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp ¡P
Bridge
segment erections ¡P
Hing
Fat Street modification works ¡P
EVA
bulkhead removal ¡P
Hing
Fat Street Slip Road Bridge E parapet construction |
¡P
Noise
level shall be controlled by reducing the breaking operation rate. ¡P
Noise
barrier shall be implemented ¡P
Dust
control during dust generating works ¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. |
HK/2009/01 |
¡P
Stage
3b backfilling works ¡P
Stage
4 construction tunnel structure ¡P
Reinstatement
of outfall ¡P
Reinstatement
of triangular planter at Fenwick Pier Street |
¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. ¡P
Dust
control during dust generating works ¡P
Noise
mitigation measures during breaking works |
HK/2009/02 |
¡P
Construction
of pre-cast concrete cover ¡P
Tunnel
OHVD construction ¡P
Tunnel
wall and top slab construction ¡P
Waterproofing
layer at side wall slap application ¡P
Road
side barrier construction ¡P
Removal
of remaining temporary sheet pile seawall ¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5 ¡P
Diaphragm
wall construction ¡P
Excavation
work ¡P
Strut
installation |
¡P
Dust
control during dust generating works ¡P
Proper
maintenance boundary surface runoff protection and water treatment
facilities to avoid potential runoff related impact. ¡P
Provision
of protection measures to ensure no runoff out of site area or direct
discharge into public drainage system. |
HK/2012/08 |
¡P
Grouting ¡P
Construction
of MVB ¡P
Pre-bored
H-pile construction ¡P
Construction
of concrete plug ¡P
Excavation
and lateral support installation for CWB tunnel |
¡P
Dust
control during dust generating works ¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system. |
HY/2010/08 |
¡P
Tree
protection works next to existing BGO, ¡P
Drainage
improvement works, ¡P
Excavation
and Lateral Support for U-structure, ¡P
Pipe
piling & grouting works, ¡P
Utility
diversion works, ¡P
Retaining
wall works ¡P
ELS
works, ¡P
D-wall
drill cutting works ¡P
Construction
works for subway extension |
¡P
Dust
control during dust generating works and stockpile stored on site. ¡P
Appropriate
measures should be taken to ensure adequate protections are provided for
trees being transplanted and retained on site. ¡P
Provision
of protection to ensure no runoff out of site area or direct discharge into
public drainage system. |
HY/2011/08 |
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building ¡P
Construction
of Tunnel Thermal Barrier ¡P
Installation
of Electricals and Mechanicals ¡P
Installation
of Tunnel Features |
¡P
Dust
control during dust generating works |
10.0.3.
The construction works of Contract no.
04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06
was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014.